The Order a Kitchen Actually Gets Done In

Almost every expensive mistake in a renovation is a right thing done at the wrong moment. Here is the sequence, step by step, with the reason each one sits where it does — including the two-week hole in the middle that nobody plans for.

🛠 20 steps⏱ 11 min read🔄 Reviewed August 2026

The floor went in last week and it looks superb. The cabinets land on Thursday. What nobody in the house knows yet is that the countertop shop will not template until those cabinets are installed and levelled, that the template is followed by eleven days of nothing, and that the sink and the backsplash are both queued behind the stone. That is not bad luck. That is the schedule, and it was set the week the order was placed.

00 Why order

Sequence is most of the job

Look at what actually goes wrong in a kitchen renovation and very little of it is craftsmanship. The tile is usually fine. The cabinets are usually square. What bites people is a correct action taken at the wrong moment: tile run up the wall before the counter exists, so the last course dies in a shadow gap that gets caulked twice a year. A dishwasher that will not come back out because the floor went in around it.

None of that takes skill to avoid — only a list, in the right order, agreed before the first wall comes down. Sequence is the one part of a renovation you can get completely right on paper, months before you own a tool.

It matters because a kitchen is a relay. Every trade waits on the one in front, so a slip does not absorb, it propagates: lose three days at rough-in and you lose your inspection slot, then the drywaller’s window, then your place in the countertop shop’s queue.

What they search at midnight “what order to renovate a kitchen” — usually typed at the exact moment two trades discover they are each waiting for the other.

The sequence

Twenty steps, and why each one sits there

The running order for a normal kitchen: same footprint or a modest change, no addition. Steps overlap in real life — a good installer trims while the electrician finishes — but the dependencies do not bend.

  • Measure the room, then design itThree heights on every wall, both diagonals for square, the ceiling checked at each end. Design to the smallest reading.Why hereEvery number downstream is quoted off this survey. Chapter 01 has the method.
  • Confirm the exact appliance modelsA model number and a saved spec sheet, not “a 30″ range”.Why hereAppliance openings size the cabinets around them, and the cabinets are built before the appliances arrive.
  • Order the cabinets, put the lead time on the calendarAsk for it in writing, then work every other date backwards from it.Why hereIt is the longest fixed block in the job, and the one you cannot compress by working weekends.
  • DemolishCabinets, counter, old flooring if it is going, wall coverings back to the studs wherever a trade has to work.Why hereNothing behind a wall can be surveyed until it is open, and what is back there changes the plan.
  • Do any structural workA wall removed, an opening widened, a header added, a sloped floor levelled.Why hereIt changes the room the cabinets were drawn into, so re-measure before anything is fixed to the new walls.
  • Rough in plumbing, electrical and ventilationDrain and supply moved to the new sink position, circuits pulled, hood duct run, blocking added where something heavy will hang.Why hereThe walls are open exactly once. Anything you skip is surface conduit or a second demolition.
  • Get the rough-in inspected, where that appliesBook it early — inspectors have queues too.Why hereThe work has to be seen before it is covered, and reopening a finished wall to prove it is its own week.
  • Insulate, drywall, tape and sandJoints finished flat — genuinely flat, because a bowed wall shows across a run of cabinets.Why hereCabinets hang on a plane. Photograph every open wall with a tape in the shot first.
  • Prime and put on the first coatCeiling and walls, including the wall that will be hidden behind cabinets forever.Why hereCutting in behind an installed wall cabinet with a brush is miserable, and it never looks right.
  • Lay the flooring — or deliberately do notThe fork in the road; both branches are legitimate. Pick before the cabinets are ordered.Why hereThe floor sets the finished height of the bases, the counter, the dishwasher opening and the toe kick.
  • Install the cabinetsWall cabinets first while the floor is clear, then bases levelled on their adjustable feet and screwed to each other before the wall, through the mounting rails.Why hereNothing can be templated until the boxes are in, level and staying put.
  • Have the countertop templatedThe fabricator measures what you actually built; sink and tap must be on site.Why hereA template records reality, not the drawing. Every stone shop refuses to template off a plan, and they are right to.
  • WaitUsually one to two weeks; longer in a busy season or for a slab that has to be brought in.Why hereThis gap is not slack in the schedule. It is the schedule, and everything downstream of the counter parks behind it.
  • Install the countertopOften half a day, and the job unlocks the moment it is down.Why hereIt is the surface the sink, tap, dishwasher, slide-in range and backsplash all attach to or reference.
  • Fit the sink, the tap and the final plumbingSink set and sealed, tap through its hole, trap and supplies connected, dishwasher hooked up.Why hereAn undermount bonds to stone that did not exist yesterday. Also the day running water comes back.
  • Tile the backsplashSet, grout, then a caulk joint — not grout — where tile meets counter.Why hereThe tile takes its bottom line off the finished counter, which is never quite the line on the drawing.
  • Bring the appliances inFridge, range, dishwasher, microwave, hood.Why hereThey need the finished floor height and the finished counter: a slide-in range rests its lips on the stone, a dishwasher fastens up into it.
  • Finish the electricalDevices and cover plates, under-cabinet lighting connected, hood wired, everything tested.Why hereCover plates want the finished backsplash behind them. Layer the lighting while you are in there.
  • Toe kicks, trim, handles and hinge adjustmentKick boards clipped on, panels scribed, handles drilled, then every door adjusted until the gaps read as straight lines.Why hereDoors get adjusted once the boxes have stopped moving and the floor is final. Earlier, and you do it twice. Where handles go.
  • Touch-up paint, then the deep cleanFill the nail holes, second coat where it needs one, then a proper clean including inside every cabinet.Why hereTile cutting, drywall sanding and trim nailing all throw dust onto anything painted before them.

Book the template the day the cabinets are delivered, and the inspection the day the rough-in is finished. Both have queues you do not control.

Where a drawing earns its keep

Steps 01 to 03 are one thing: turn the room into numbers you trust before you spend anything. That is what our planner does — draw the real room, place real catalogue cabinets at the sizes that exist, check it in plan, 3D and elevation, and ask the assistant, Emma, rather than hunt through menus. It will not book your inspector. It will stop you drawing a cabinet no factory makes.

02 Decide early

Four decisions that feel much too early

Some choices sit uncomfortably far forward. They feel like finishing touches — a sink, a hood, the colour of the floor — and they are structural, because something gets built or cut to suit them.

  • The exact appliance models — before the cabinets are ordered. A fridge needs a rough opening wider than its body plus air at the back and top; a slide-in range needs a specific cutout. Design to the marketing size and the appliance does not go in.
  • The hood and its duct route — both, together. The hood decides the cabinet above it and sometimes whether that cabinet exists; the duct decides where a hole goes through a joist, a wall or a roof, which is rough-in work. Allow 30″ from the cooking surface to an unprotected cabinet, and mount hoods roughly 24–30″ above gas or 20–24″ above electric. The rest of the appliance numbers.
  • The sink and the tap — bought and on site before the template. The bowl cutout and the tap holes are made in the shop, on a saw, from your actual fixture. Change your mind after fabrication and you are buying stone, not a sink. Choosing between the types.
  • Floor before or after the cabinets — it changes the finished height of every base cabinet, the counter, the dishwasher opening and the toe kick.

What they share is a manufacturing step downstream. A cabinet is made to an appliance opening. A slab is cut to a sink. A toe kick is cut to a floor. Each has to be settled before the machine runs, and “we will pick that later” is the most reliable predictor of a delay we know.

03 The wait

The countertop gap is your schedule

The most misunderstood thing about kitchen renovations: in the middle of every one sits a gap of one to two weeks in which very little can happen, and it is nobody being slow.

A countertop cannot be measured until the cabinets are installed, levelled and permanent, because the fabricator records the room as built — walls that are not straight, a run that is a shade long, a corner that is not quite 90°. That measurement is the template. Then the slab joins a shop queue to be cut, edged, polished and holed. In between you have base cabinets, no worktop, no sink and no dishwasher — and because so much hangs off the counter, the gap blocks a surprising amount of the job.

Waits for the countertopWhy it cannot go firstWhat it holds up in turn
Sink & tapHoles are cut in the shop from your actual fixtures; an undermount bonds to the stoneRunning water in the kitchen
Final plumbingTrap, supplies and the dishwasher drain connect to a now-permanent bowl positionThe dishwasher, the disposal
DishwasherIt fastens up into the counter, or to the cabinet sides where the top is stoneNothing — but you have no dishwasher until then
Slide-in rangeIts side lips are made to land on the finished counterThe final gas or electrical connection
BacksplashThe tile takes its bottom line from the counter as installed, not as drawnCover plates, under-cabinet lighting
Cover plates & devicesThe finished tile has to be the surface behind themFinal electrical sign-off, where one applies

None of it is avoidable, so plan for it rather than discovering it. Get your name into a fabricator’s book while the walls are still open, and ask what their template-to-install turnaround is running at right now — it varies by season and by material, and a shop that gives you a straight number is a good sign. If a fortnight with no worktop is genuinely unworkable, a sheet of plywood screwed lightly to the cabinet run and a plastic basin will hold the household together.

04 The floor

Flooring before or after the cabinets

The question we are asked most, and the honest answer is that both are defensible and professionals argue about it in good faith. What is not defensible is leaving it open, because the choice changes the finished height of everything.

Option A

Floor first, cabinets on top

The safer default for tile, engineered wood and vinyl plank

The floor runs wall to wall and the cabinets sit on it. Most installers prefer this, and the reason is the dishwasher.

What you gain
  • The dishwasher pulls straight out for service in ten years, because its opening is not ½″ shorter than on delivery day
  • No thresholds or filler strips where the floor dies at a toe kick
  • You can change the layout later without patching
What it costs you
  • Material under cabinets you will never see
  • The floor lives through the rest of the job and needs protecting properly — hardboard, not a dust sheet
Option B

Cabinets first, floor around them

Reasonable when the floor is already down, or must not be wasted

Cabinets go on the subfloor; the floor is laid up to the toe kick afterwards. Nothing is buried and no trade walks on it.

What you gain
  • No material under the boxes
  • The finished floor arrives late and stays pristine
  • Sensible when you are keeping a floor in good condition
What it costs you
  • The dishwasher opening must be sized with the future floor thickness subtracted, or the machine never comes back out
  • Every cut around a toe kick is fussy and visible

With Option B, write the floor build-up on the plan — finish plus underlay — and size the dishwasher opening around it. A dishwasher is a snug fit under a standard counter already; take ½″ with flooring and another ¼″ with underlay and it goes in tilted, or not at all. Adjustable feet can raise a cabinet. Nothing raises a counter that is already down.

The floating floor exception

Laminate and click-together engineered floors are not fastened down — they float, and they expand and contract seasonally across their whole area. They must not be trapped under cabinets. A run of bases screwed through a floating floor pins it in the middle of the room, and the movement that has nowhere to go comes out as buckled seams or lifted planks somewhere else. Install on the subfloor, bring the floor up to the toe kick, and leave the expansion gap the manufacturer asks for. This one is not a preference.

05 Your limits

What to do yourself, and where to stop

A capable DIYer can do most of a kitchen. Demolition is mostly patience and a reciprocating saw. Hanging frameless cabinets is careful, methodical work rather than skilled work: find the studs, strike a level line, hang the wall cabinets first, then set the bases on their adjustable feet and screw them to each other before the wall. Backsplash tile, handles, paint, vinyl plank — all reasonable weekend work with a day of practise first. Then there are four places where we would stop, and we say that as people who make cabinets rather than people selling labour.

  • GasMoving, capping or connecting a gas line is licensed work almost everywhere, and the failure mode is not a drip you notice under the sink. Switching from electric to gas means a licensed fitter and usually a permit.
  • The main electrical panelPulling cable in an open wall is one thing; landing a new circuit in the panel is another, and the service lugs stay live with the main breaker off. A kitchen typically needs dedicated circuits for the range, dishwasher and disposal.
  • Anything holding the ceiling upWidening a doorway or taking out a wall needs someone to determine whether it is load-bearing and to size the header, temporary support included. That is an engineer or a contractor prepared to put their name to it.
  • Permits and inspectionsNot a skill question — a jurisdiction question. Cabinets in the same footprint often need nothing; moving plumbing, adding circuits, altering a wall or touching gas frequently does, and the rules differ between two towns an hour apart. Ask your building department.

To be blunt about the limits of an article, this one included: nothing written for a general audience can tell you what your local code requires, whether your wall carries load, or whether your wiring is fit to extend. Those get answered by someone standing in your kitchen. An article can only say which questions to ask, and when.

06 No kitchen

How long you are really camping, and what stretches it

People arrive expecting two weeks. For a straightforward kitchen with no structural work, four to eight weeks from the first day of demolition to the final clean is the honest range, with the cabinet lead time in front of it. You are not without a kitchen that whole stretch — but you are without a sink for much of it, and the sink is the thing people miss.

Set the temporary kitchen up the day before demolition, not the evening you discover you have nowhere to make coffee. It wants four things: the fridge, moved to the dining room or garage; a heat source, meaning a kettle, a microwave and a toaster oven or single induction hob; a washing-up station, in practice the bathroom sink or a laundry tub; and a bin plan, because renovation weeks generate an astonishing amount of packaging. Pack everything else away — whatever is left in the kitchen is under drywall dust within a day — and hang a zippered dust barrier at the doorway.

As for where the calendar slips, it is nearly always one of four things, and three of them are foreseeable.

  • Appliance lead timesThe one everybody underestimates. A particular fridge in a particular finish can be weeks or months out, and because its rough opening sizes the cabinet around it, you cannot substitute freely at the last minute.
  • What was actually behind the plasterThe unforeseeable one. A vent stack in the wall you meant to remove, wiring that has to be replaced rather than extended, no header where a previous owner made an opening. Demolition is when this surfaces, which is why it should be early and thorough.
  • The fabricator’s queueTemplate to installation is not a fixed number. It stretches in busy months, and further if your slab has to be brought in. Ask for the current turnaround when you book.
  • A decision nobody madeThe most common and the most avoidable. The sink was not bought before the template. The handles were never chosen, so the doors go on undrilled. Every open decision eventually becomes a stopped trade.
07 Before demolition

The list to clear before the first wall comes down

Demolition is the point of no return: the moment it starts, you are on the clock and the family is cooking on a folding table. Everything below should be true before that morning.

  • Every appliance confirmed by model number — spec sheets saved, rough openings on the plan, and each model available now rather than when you started looking.
  • Cabinets ordered, lead time in writing — with a delivery date on the calendar. Never demolish a working kitchen against a date nobody has given you.
  • Sink and tap bought and in the house — they have to be present for the template, which is weeks away and then arrives at short notice.
  • Hood and duct route decided — including where the duct leaves the building and what it crosses on the way.
  • Flooring chosen, bought and acclimatising — most wood and laminate wants a few days lying in the room before it goes down, and nobody schedules that.
  • The permit question answered by the building department — by them, in a phone call. Not by a forum, and not by us.
  • Shutoffs found and tested — water main, the kitchen’s own valves if it has them, the gas valve, and a panel whose circuits are actually labelled.
  • Somewhere dry and flat to stack the cabinets — off bare concrete, out of the work zone, not in the room about to be tiled.
  • Photographs of every wall — before demolition and again with the walls open, tape measure in the frame. Three years from now, hanging a shelf, they beat the drawings.
  • A waste route decided — including a plan for the old cabinets, which do not fit in a bin bag and will not leave through a tidy house on their own.

If every line is true, the rest is execution in a known order. If two or three are still open, spend one more week on paper — the only week in the whole project where nobody is waiting on you. When something does go sideways mid-job, there is a chapter for that too.

? People also ask

Straight answers

What order should a kitchen renovation be done in?+

Measure and design, confirm appliance models, order cabinets, demolish, complete any structural work, rough in plumbing, electrical and ventilation, pass inspection where it applies, insulate and drywall, prime and put on the first coat of paint, lay flooring if it is going in first, install cabinets, template the countertop, wait for fabrication, install the countertop, then sink and tap, backsplash, appliances, final electrical, toe kicks and trim and handles, and finally touch-up paint and the clean.

Does flooring go in before or after kitchen cabinets?+

Both are defensible. Floor first gives a continuous floor, a dishwasher that can be pulled out for service years later, and freedom to change the layout without patching; it uses material you will never see and the floor has to survive the rest of the job. Cabinets first wastes nothing and keeps the new floor pristine, but the dishwasher opening has to be sized with the future floor thickness allowed for. Floating floors are the exception: they must not be trapped under cabinets, because they have to move.

When should I order my countertops?+

The stone cannot be ordered until the cabinets are installed and level, because the fabricator templates the room that exists rather than the room on the drawing. What you should do early is choose the material, get your name into the shop's queue while the walls are still open, and buy the sink and tap so they are physically on site for the template. Expect roughly one to two weeks between template and installation.

How long does a kitchen renovation take?+

For a straightforward kitchen with no structural work, four to eight weeks from the first day of demolition to the final clean is realistic, and the cabinet lead time sits in front of that. The largest single fixed block inside the schedule is the countertop gap between template and installation.

How long will I be without a kitchen?+

Longer than the demolition and shorter than the whole job. Plan on three to six weeks with no sink and no worktop for a typical renovation. A fridge, a kettle and a microwave can be running again within days of demolition; the sink is the one you wait for, because it comes back only after the countertop is installed.

When do I have to choose my appliances?+

Before the cabinets are ordered, and by model number rather than by category. The rough opening for a fridge, the cutout and lip of a slide-in range, the hood's duct size and the dishwasher's height all set cabinet dimensions, and cabinets are built long before appliances are delivered. Swapping models afterwards is a redesign, not a substitution.

Do I need a permit for a kitchen renovation?+

It depends on where you live and on what you are actually doing. Replacing cabinets in the same footprint often needs nothing; moving plumbing, adding circuits, altering a wall or touching a gas line frequently does, and the rules differ between neighbouring towns. The only reliable answer comes from your local building department, and it is one phone call. Any article that gives you a firm yes or no is guessing.

When does the backsplash go in?+

After the countertop, always. The tile takes its bottom line from the counter as installed, which is never exactly the line on the drawing, and the joint between tile and counter should be caulk rather than grout so it can move. Tiling first means cutting to a surface that does not exist yet and living with a gap you fill again every year.

Can I install kitchen cabinets myself?+

Many people can. Hanging frameless boxes is careful, methodical work rather than skilled work: find the studs, strike a level line, hang the wall cabinets first, then set the base cabinets on their adjustable feet, clamp them face to face and screw them to each other before screwing them to the wall through the mounting rails. What we would not take on without a licensed trade is gas, the main electrical panel, and any opening in a wall that might be carrying load.